Every phase ends with something you sign. Nothing moves forward on a verbal “looks good”, because that is the sentence every disputed software invoice starts with.

Section 01 · The phases

From first call to handover.

Phase 00

Scoping call — free

Forty-five minutes on the product, the users, the money model and the deadline. You get: an honest read on whether it should be built, and whether we are the right people to build it.

45 minutes
Phase 01

Validation sprint

Discovery, flows, prototype, UI design, functional specification and architecture outline. Gate: you sign off the specification. You keep it whether or not you build with us.

2–3 weeks
Phase 02

Fixed-price Statement of Work

Scope, deliverables, architecture, milestones, dates, acceptance criteria and one number. Gate: countersignature plus the 30% mobilisation instalment.

3–5 days
Phase 03

Design & architecture

Final UI, data model, API contract and infrastructure stood up in your accounts. Gate: design sign-off plus the second 30%.

1–2 weeks
Phase 04

Engineering sprints

Two-week cycles, each ending in a demo on staging and a written build note. Out-of-scope items become priced change requests before they are built.

Bulk of build
Phase 05

UAT & hardening

You test against the acceptance criteria. Defects are fixed at our cost; new ideas become phase two. Gate: UAT sign-off plus the third 30%.

1–2 weeks
Phase 06

Launch & handover

Production deployment, monitoring, documentation, team walkthrough, and the 60-day warranty clock starts. Gate: final 10%.

Go-live
Section 02 · Payment

Thirty, thirty,
thirty, ten.

Tied to gates rather than to the calendar. We are never more than one instalment ahead of delivered work, and the final tranche is only due once the product is live.

Instalment 01

30% — on SOW signature

Mobilisation: team allocated, environments created, architecture work begun.

Instalment 02

30% — on design sign-off

Full UI, data model and API contract approved by you before engineering scales up.

Instalment 03

30% — on UAT sign-off

The product meets the acceptance criteria in the SOW, tested by you on staging.

Instalment 04

10% — on go-live

Deployed to production, handover complete, documentation delivered.

Section 03 · Change control

How changes are
handled, in four rules.

This is where fixed-price engagements normally break down. Writing the rules in advance is what stops it happening.

  1. Anything not in the specification is a change. Including things everyone assumed were obvious. That is not pedantry — it is the only way a fixed price can mean anything.
  2. Every change is quoted in writing first. Cost, timeline impact and any knock-on effect on other items, before a line of code is written.
  3. You approve or decline. Nothing is assumed. Declined changes go into the phase-two backlog rather than disappearing.
  4. Defects are never changes. If it does not match the acceptance criteria, it is our problem and it is fixed at our cost.

What counts as a defect

  • Behaviour that contradicts the written acceptance criteria
  • A feature in the spec that does not work as described
  • Errors, crashes or data loss under normal use
  • A documented browser or device where it does not function

What counts as a change

  • A feature that is not in the specification
  • A different rule, threshold or workflow than the one signed off
  • A new integration, platform or user role
  • Design revisions after design sign-off
  • Scope added because a third party changed its API mid-build

What we need from you

  • One named decision-maker who can sign off scope and design
  • Availability for the discovery workshops in phase 01
  • Access to any existing systems we must integrate with
  • Sign-off turnaround within five working days at each gate
  • Someone to run UAT properly against the criteria
  • Honest answers about budget and deadline constraints

What you get from us

  • A specification you own, whether or not you build with us
  • One fixed price, in writing, before build starts
  • A demo and a written note every two weeks
  • Change requests priced before any work is done
  • Delays disclosed in the week they occur
  • Full handover, documentation and a 60-day warranty
5 dayssign-off turnaround needed at each gate
14 dayssprint length, each ending in a live demo
60 daysdefect warranty from go-live
0changes built without written approval
Next step

Bring us the idea. We’ll bring back a scope you can hold us to.

A scoping call costs nothing and takes forty-five minutes. If the product does not need building yet, or needs building by someone else, we would rather say so in that call than three months into a contract.

Book a scoping call Call +91 99944 61072 Free · No obligation · NDA on request